Demo Project — Commercial Tenant Improvement

Multi-discipline (Architectural / Electrical / Mechanical) Canada — Alberta 4 sheets
📋Overall readiness: Needs revision
2
Critical
3
High
2
Medium
1
Low
📄 PDF 📝 Word 📌 Bluebeam (XFDF)

Executive Summary

  • Overall readiness: Needs revision
  • Suitable for: Coordination and pricing discussion — not yet ready for building permit or construction.
  • Top 5 risks:
    1. Climatic design data on the cover sheet is for the wrong city — every snow, wind, and seismic value downstream is suspect.
    2. No seismic restraint shown for roof-mounted mechanical units (NBC 4.1.8.18).
    3. Electrical room working clearance in front of the new 600 A distribution does not meet CEC 2-308.
    4. Egress: occupant load and travel-distance analysis are absent, so exit capacity can't be verified.
    5. Barrier-free washroom clear floor space and mirror height are non-compliant as drawn.
  • Biggest missing information:
  • Occupant load and egress capacity table
  • Coordinated mechanical/electrical penetration schedule through the 2-hr demising wall
  • Complete door/finish schedules with fire-protection ratings

Major Findings

# Severity Sheet/Detail Issue Engineering Risk Recommended Action Confidence
1CriticalA-001 Cover — Climatic Data tableSnow/wind/seismic values are listed for Fort McMurray, but the project address is in Calgary. Every load-dependent element inherits the error.Under- or over-designed structure and envelope; permit rejection.Replace climatic data with Calgary values (NBC Appendix C) and re-verify all dependent calcs.High
2CriticalE-301 — New 600 A distribution, Electrical Room 112Clear working space in front of the panel scales to ~900 mm; CEC 2-308 requires 1.0 m for this voltage/condition, measured clear of the door swing.Shock/arc-flash hazard; AHJ will not energize.Relocate panel or revise room layout to provide ≥1.0 m clear working space, door swing excluded.High
3HighM-201 — RTU-1, RTU-2 on roofNo seismic restraint or curb anchorage detail shown for roof-mounted units.Equipment displacement in a seismic event; NBC 4.1.8.18 non-compliance.Add manufacturer-rated seismic restraint/curb anchorage details and reference the governing detail.Medium
4HighA-101 — Overall planNo occupant load table; egress capacity and travel distance not calculable.Life-safety exits cannot be verified; permit rejection.Add occupant load (NBC 3.4.2.2) and an egress diagram with travel distances on a code-analysis sheet.Medium
5HighA-101 — 2-hr demising wall vs. M/E penetrationsMechanical ducts and electrical conduit cross the rated demising wall with no firestop detail or assembly reference.Uncontrolled fire/smoke spread between tenancies.Add typical firestop details with listed assembly numbers; coordinate duct/conduit penetrations.Medium
6MediumA-401 — Barrier-free washroomMirror bottom shown at 1100 mm AFF; clear floor space beside the WC is not dimensioned.Accessible washroom non-compliance (CSA B651).Set mirror bottom ≤ 1000 mm AFF and dimension the 900 × 1500 mm clear floor space.High
7MediumE-201 — LightingEmergency/egress lighting and exit signage not shown on the plan.Egress illumination may be missing at inspection.Add emergency lighting and exit-sign layout per NBC 3.4.5 and the provincial amendments.Medium
8LowA-101 — Door swingsDoor swing direction not indicated on several doors along the egress path.Doors may open against travel; affects barrier-free maneuvering.Add swing symbols and confirm direction meets egress + barrier-free clearances.Medium

RFIs to Send Back

# RFI Question Why It Matters Drawing Reference
1 Confirm the project's governing climatic data location. The cover sheet lists Fort McMurray — should this be Calgary? Drives every snow/wind/seismic value in the set. A-001 Climatic Data table
2 Provide the intended major occupancy classification, building area, and occupant load per area. Determines egress, fire separation, and sprinkler requirements. Entire set
3 Are RTU-1 and RTU-2 restrained for seismic? Provide curb anchorage/restraint details. Required by NBC 4.1.8.18. M-201 roof plan
4 Confirm clear working space in Electrical Room 112 with the door in the open position. CEC 2-308 working clearance compliance. E-301

Cross-Discipline Coordination Checks

Item What to Compare Status Concern
Structural support for RTU curbs Roof framing vs. unit weight + seismic loads Not shown Framing may be inadequate for restrained units.
M/E penetrations through 2-hr wall Duct/conduit routing vs. firestop assemblies Not coordinated Rated separation likely compromised.
Electrical room vs. mechanical Panel clearance vs. duct drops above the room Possible conflict Ductwork may further reduce working space.

Missing Information

  • Occupant load and egress capacity table.
  • Door, finish, and fire-protection rating schedules.
  • Firestop details for rated-wall penetrations.
  • Emergency lighting and exit-sign layout.

This is an illustrative sample produced by Redliner's first-pass review. It is not a stamped engineering review and does not replace sign-off by a licensed professional engineer.